December, 2022

Second floor column

After completing the first floor columns and first floor, we started working on the second floor column in December 2022.

December, 2022

September, 2022

 First Floor Column

With such a long and hefty work area, it takes us more than a month to complete the process. We started pouring the content in columns in September 2022.

September, 2022

August, 2022

Ground floor Slab

After completing the Ground floor column , we shifted to the ground floor Slab in August 2022. Columns are to support floors and roof beams. So the ground floor supports the floor above it.

August, 2022

July, 2022

Ground floor column

After completing the basement slab, we shifted to the ground floor column in July 2022. Columns are to support floors and roof beams. So the ground floor supports the floor above it.

July, 2022

June, 2022

Basement Slab

A concrete basement without footings is known as a slab basement and is not similar to a foundation. We started this step in June 2022.

June, 2022

May,2022

Basement slab reinforcement

It took us several weeks to complete the Basement column pouring. The team did it well. The floor now stands strong. And we are ready to proceed tot the next stage .

May,2022

April, 2022

Basement column pouring

Zen Apartments started with basement columns in April 2022. The process seems easy but requires great caution to get durable and rigid columns. 

April, 2022

December ,2021

Basement retaining wall

It took us several weeks to complete the ground floor slab. The team did it well. The floor now stands strong. And we are ready to proceed tot the next stage – first floor column.

December ,2021

November , 2021

Raft pouring

Rafting is a long process, especially for a project like Zen Apartments. We started this phase in November 2021. This phase includes heavy machinery like truck mixers and concrete pumps.

November , 2021

October , 2021

Raft basement
We started rafting in October 2021. A raft foundation is a slab resting on the soil and extending over the entire footprint of a building. It is primarily used where the soil is weak.

October , 2021

September , 2021

Lean Foundation

In September, we started the lean foundation for Zen Apartments with the help of RMAAC Developers.

September , 2021

August , 2021



Retaining Wall Steel Binding

Followed by excavation, we started the steel binding for retaining . Retaining walls are built after excavation or land
filling to provide support and prevent the soil from eroding or
collapsing.

August , 2021

July , 2021

Excavation

The excavation for Zen Apartments at the Barian Valley in Nathiagali. Excavation is performed to uncover the depth of the soil. Clearing a construction site of unwanted bushes, weeds, and other plants is performed to prepare a building site for building contractors to erect a structure.

July , 2021